How Long Is a Florida Building Permit Good For?

A Florida building permit does not last forever. If work never starts, stops for too long, or never gets a final inspection, the permit can expire or stay "open" on the property record for years. Here is how the timing works under the Florida Building Code and the Florida Statutes, and what it means if you sell to people who pull permits.

The short answer

  • Work must start within six months. Under Section 105.4.1 of the Florida Building Code, Building (2023, 8th edition), a permit becomes invalid unless the authorized work begins within six months after it is issued.
  • Work cannot stall for six months. The same section voids a permit if the work is suspended or abandoned for six months after it starts.
  • Inspections keep it alive. Section 105.4.1.3 ties continued validity to inspections. Miami-Dade's building code office describes it as an automatic 180-day extension after each approved inspection.
  • Single-family homes have a 2026 rule. Since July 1, 2026, a permit issued by a local government for a single-family dwelling expires 1 year after issuance or on the effective date of the next edition of the Florida Building Code, whichever is later (s. 553.79(1)(c), F.S.).

Chapter 1 of the building code covers administration, and many cities and counties adopt their own version of it, so the building department that issued the permit has the final word on its own deadlines.

The 2026 single-family rule

House Bill 803, passed in the 2026 session, added the one-year single-family rule to s. 553.79 and to the county permitting statute, s. 125.56(4)(d). Two points matter in practice:

  • It covers single-family dwellings only. Other permits still follow the code's six-month and inspection rules.
  • In a June 30, 2026 memo, Miami-Dade's Board and Code Administration Division said the one-year period applies only to the initial validity period, when no activity has occurred. Once work starts, each approved inspection extends the permit for another 180 days.

The next edition is close: the 2026 Florida Building Code (9th edition) takes effect December 31, 2026. Under s. 553.73, F.S., the code edition in effect when the permit application was submitted governs the permitted work for the life of the permit and any extension, so applications first submitted on or after that date must meet the new edition.

Expiration notices and extensions

  • Notice is optional. Under s. 553.79(1)(c), a local government may send a written notice of expiration, by email or U.S. mail, to the property owner and the contractor on the permit no less than 30 days before the permit expires. The notice must identify the permit and its expiration date. Do not count on receiving one.
  • Extensions are allowed. The same paragraph says it does not prevent a local government from extending a permit beyond its expiration date. Each department sets its own process and fee, so ask before the deadline passes.
  • Emergencies can extend deadlines. After a governor's emergency declaration, such as for a hurricane, s. 252.363, F.S. can extend permit deadlines. Check the terms of each declaration.
  • A void permit means a new permit. Under Section 105.4.1.2 of the code, if a new permit is not obtained within 180 days after the original became void, the building official may require the work already done to be removed, or may issue a new permit if the work in place meets the applicable rules.

Open, expired and closed permits

An open permit was issued but never received a final inspection. An expired permit lapsed before the work was finished and approved. Either one can surface when a property is sold or refinanced. Florida law offers several ways to clear them:

  • The property owner can close a permit by keeping the original contractor, hiring another licensed contractor, or acting as owner-builder where the law allows (s. 553.79(16)(a)).
  • If the work under an expired permit was substantially completed, the building department may close it without a new permit (s. 553.79(16)(b)).
  • The building department may close a permit 6 years after issuance, even without a final inspection, if it finds no apparent safety hazards (s. 553.79(16)(c)).
  • A buyer who purchased for value in an arm's-length sale cannot be denied a permit, cited or fined solely because a previous owner's permit was never closed. The department keeps its remedies against the owner and contractor listed on the permit (s. 553.79(17)(a)).
  • A contractor cannot be denied a permit solely because it is listed on other permits that were not closed (s. 553.79(17)(b)).

Why this matters if you sell to permit holders

  • Inspection history shows momentum. A permit with recent approved inspections is a live job. Time your offer to the stage the project has reached.
  • Stalled permits can need a new contractor. When inspections stop for months, the owner may be looking for someone to finish and close the job, which the statute expressly allows.
  • New permits come with a clock. Because work has to start within six months of issuance, a newly issued permit is a project that should begin soon, which is the best moment to reach the owner.

This guide is general information, not legal advice. The rules of the building department that issued the permit control.

Permit Radar FL turns the new permits issued by Miami-Dade County's building department into a downloadable list filtered by trade, refreshed weekly from the county's public records, so you reach active projects first. Since 21 November 2026 it also includes permits issued by the City of Miami; other city departments are not included yet. To look up one property, see Miami-Dade permit search.

Related: how to check a property's permit history. Contractors can see this week's new Miami-Dade permits by trade with the free permit check.